Ireland
Ireland's data-centre permitting path is grid-first and multi-track. A developer engages the electricity system operators early under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data-centre connection direction), which conditions any new connection offer on dispatchable generation or storage matched to import capacity and on sourcing at least 80 percent of annual demand from new Irish renewable generation within six years of energisation. Planning permission goes to the local planning authority in the first instance, because the 2018 provision that would route large data centres directly to the national planning body as strategic infrastructure has not been commenced; appeals go to An Coimisiun Pleanala, the renamed An Bord Pleanala. There is no dedicated data-centre EIA class, so environmental impact assessment is triggered through the general screening duty where significant effects are likely. Standby generation fleets over a combined 50 MW thermal input need an EPA industrial emissions licence, building control runs in parallel with planning, and water and wastewater connections come from Uisce Eireann under a CRU-approved charging policy. Government policy overlays the path without adding consents: the July 2022 Government Statement and the January 2026 Large Energy User Action Plan favour renewable-co-located, grid-efficient projects.
National jurisdiction. Reviewed 2026-07-24.
The permitting path
Ireland's path runs grid-first: under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data centre connection direction), a new connection offer requires dispatchable generation or storage matched to the facility's import capacity and a commitment to source at least 80 percent of annual demand from new Irish renewable generation within six years of energisation. Planning permission sits with the local authority in the first instance (the 2018 provision routing large data centres directly to the national planning body is not yet commenced), with appeals to An Coimisiun Pleanala, and environmental impact assessment where screening requires it. Uisce Eireann water and wastewater connections, building control certificates, and an EPA industrial emissions licence for standby fleets over 50 MW thermal complete the path.
| # | Step | Authority level | Legal basis |
|---|---|---|---|
| 1 | Grid connection application | utility | Large Energy Users Connection Policy (CRU/25/236), under the Electricity Regulation Act 1999 |
| 2 | Connection offer and agreement | utility | Connection offer issued by EirGrid or ESB Networks under the CRU Large Energy Users Connection Policy (CRU/25/236) |
| 3 | Dispatchable generation or storage matched to import capacity applies for new connection applications under the 2025 policy |
regulator | Connection policy requirement (CRU/25/236): onsite or proximate dispatchable generation or storage matching import capacity, participating in the Single Electricity Market |
| 4 | Renewables matching commitment (80 percent in six years) applies for new connection applications under the 2025 policy |
regulator | Connection policy requirement (CRU/25/236): at least 80 percent of annual demand from new Irish renewable generation within six years of energisation |
| 5 | Strategic infrastructure pre-application consultation applies where an associated Seventh Schedule class, such as large scale onsite generation, routes the application to An Coimisiun Pleanala; the data centre specific route is not yet commenced |
national | Planning and Development Act 2000, strategic infrastructure provisions |
| 6 | Environmental impact assessment applies where screening determines significant effects are likely |
local | Sections 176A to 176C, Planning and Development Act 2000; Planning and Development Regulations 2001 (S.I. No. 600 of 2001) screening |
| 7 | Planning permission | local | Planning and Development Act 2000 (as amended); Planning and Development Act 2024 |
| 8 | Uisce Eireann wastewater connection | utility | Water Services Acts 2007 to 2017 |
| 9 | Uisce Eireann water connection agreement | utility | Water Services Acts 2007 to 2017; CRU-approved connection charging policy |
| 10 | Building control (commencement notice; fire safety and disability access certificates) | local | Building Control Acts 1990 to 2014 |
| 11 | EPA industrial emissions licence applies where standby generation crosses licensing thresholds |
national | Environmental Protection Agency Act 1992; Industrial Emissions Directive as transposed |
Steps are shown in their typical order; steps at the same stage usually run concurrently, and conditional steps apply only where noted. Per-facility status against this path is tracked at ComputeCompute.
Building Control Acts 1990 and 2007
Building control runs in parallel with planning: a commencement notice before construction starts, a fire safety certificate, a disability access certificate where applicable, and a certificate of compliance on completion, administered by the local building control authority.
- Citation
- No. 3 of 1990 and No. 21 of 2007; Building Control (Amendment) Regulations 2014 (S.I. No. 9 of 2014)
- Status
- In force
- Applies to
- Both
- Source
- No. 3 of 1990 and No. 21 of 2007; Building Control (Amendment) Regulations 2014 (S.I. No. 9 of 2014)
Electricity Regulation Act 1999
The statutory basis for the Commission for Regulation of Utilities and for licensing of generation and supply; the legal foundation under which the CRU issues its connection-policy decisions.
- Citation
- No. 23 of 1999, as amended
- Status
- In force
- Applies to
- Both
- Source
- No. 23 of 1999, as amended
Large Energy User Action Plan (LEAP)
A plan-led framework of 17 actions for locating large energy users, including data centres, proposing green energy parks that co-locate demand with renewable generation. Government policy rather than legislation; it operationalises the 2022 statement alongside the CRU's connection policy.
- Citation
- Department of Enterprise, Tourism and Employment, 13 January 2026
- Status
- In force
- Effective date
- 2026-01-13
- Applies to
- Government
- Source
- Department of Enterprise, Tourism and Employment, 13 January 2026
Large Energy Users Connection Policy (CRU/25/236)
The operative connection policy for data centres and other large energy users. New connection applications require onsite or proximate dispatchable generation or storage matched to import capacity, participation in the Single Electricity Market, and a commitment to source at least 80 percent of annual electricity demand from new Irish renewable generation within six years of energisation. Applications made before the decision continue under the 2021 direction.
- Citation
- CRU/25/236, decision of 12 December 2025
- Status
- In force
- Effective date
- 2025-12-12
- Applies to
- Private sector
- Source
- CRU/25/236, decision of 12 December 2025
Planning and Development Regulations 2001 (EIA screening)
Schedule 5 has no dedicated data-centre class, so environmental impact assessment is typically required through the sub-threshold screening duty: the planning authority or An Coimisiun Pleanala must screen any development likely to have significant environmental effects, including cumulative effects with grid and onsite-generation works.
- Citation
- S.I. No. 600 of 2001, Schedule 5, with sections 176A to 176C of the 2000 Act
- Status
- In force
- Effective date
- 2001-12-21
- Applies to
- Both
- Source
- S.I. No. 600 of 2001, Schedule 5, with sections 176A to 176C of the 2000 Act
Government Statement on the Role of Data Centres in Ireland's Enterprise Strategy
Cross-government principles for assessing data-centre development: preference for projects with strong economic activity, efficient grid use, and co-location with renewable generation. A statement of policy rather than a consent requirement; it is now read alongside the 2025 connection policy and the 2026 Large Energy User Action Plan.
- Citation
- Government of Ireland policy statement, July 2022
- Status
- In force
- Effective date
- 2022-07-01
- Applies to
- Government
- Source
- Government of Ireland policy statement, July 2022
Planning and Development Act 2000
Ireland's core planning code. Data-centre applications go to the local planning authority in the first instance: the 2018 amendment that would add large data centres (over 10,000 square metres) to the strategic infrastructure classes heard directly by the national planning body has not been commenced as of this review. Appeals lie to An Coimisiun Pleanala.
- Citation
- No. 30 of 2000, as amended; strategic infrastructure route at sections 37A to 37J
- Status
- In force
- Applies to
- Both
- Source
- No. 30 of 2000, as amended; strategic infrastructure route at sections 37A to 37J
EPA industrial emissions licensing (First Schedule, Class 2.1)
Combustion installations with a total rated thermal input of 50 MW or more require an industrial emissions licence from the EPA. A data centre's standby generator fleet is aggregated for the threshold, so large campuses hold IE licences; Amazon Data Services Ireland's licence P1186-01 at Clonshaugh, Dublin is a published example.
- Citation
- Environmental Protection Agency Act 1992 (No. 7 of 1992), First Schedule, Class 2.1
- Status
- In force
- Applies to
- Both
- Source
- Environmental Protection Agency Act 1992 (No. 7 of 1992), First Schedule, Class 2.1
Water Services Acts 2007 to 2022 (Uisce Eireann connections)
Uisce Eireann is the single national water and wastewater utility. A data centre's water and wastewater connections are applied for under its CRU-approved connection charging policy through the standard non-domestic connection process.
- Citation
- Water Services Act 2007; Water Services (No. 2) Act 2013; Water Services (Amendment) Act 2022; CRU-approved connection charging policy
- Status
- In force
- Applies to
- Both
- Source
- Water Services Act 2007; Water Services (No. 2) Act 2013; Water Services (Amendment) Act 2022; CRU-approved connection charging policy
Planning and Development Act 2024
A phased recast of the planning code. An Coimisiun Pleanala replaced An Bord Pleanala with effect from 18 June 2025; the chapters reworking development consents and strategic infrastructure procedure were not yet fully commenced at this review.
- Citation
- No. 44 of 2024, phased commencement
- Status
- Enacted, not yet in force
- Effective date
- 2024-10-17
- Applies to
- Both
- Source
- No. 44 of 2024, phased commencement
Direction on data centre grid connection processing (CRU/21/124)
Directed EirGrid and ESB Networks to apply assessment criteria, including grid constraint at the location, onsite generation, and demand flexibility, before making any data-centre connection offer. Superseded by CRU/25/236 for new applications; pre-existing applications continue to be processed under it.
- Citation
- CRU/21/124, direction of November 2021
- Status
- Superseded
- Effective date
- 2021-11-23
- Applies to
- Private sector
- Source
- CRU/21/124, direction of November 2021
Reviewed 2026-07-24. Confidence: high. Fast-moving area, verify before relying. Not legal advice.