California

California runs environmental review together with the land-use entitlement: the city or county acting on the conditional use permit or site plan is usually the CEQA lead agency, so the two decisions move as one record. Large onsite generation adds a California Energy Commission authorization under the Warren-Alquist Act. Water service commitments for large projects carry statutory assessments under SB 610 and SB 221, air districts permit the generator fleets, and the State Water Board's construction general permit covers site disturbance of an acre or more. Fiscal terms, where they exist, are development agreements under the Government Code. California has no data-center-specific permitting statute as of this review; bills touching data-center energy and water reporting have been introduced in recent sessions.

Subnational jurisdiction. Reviewed 2026-07-24.

9
Instruments
high
Confidence

The permitting path

California runs environmental review with the land-use entitlement: the lead agency for CEQA is usually the land-use authority, so the two milestones move together. Large onsite generation adds a California Energy Commission authorization.

# Step Authority level Legal basis
1 Site control (deed or lease) local Gov. Code 27280 (instruments affecting title recorded with the county recorder); local applications require owner authorization
2 CEQA review local Pub. Res. Code 21000 et seq.; the land-use authority is usually the lead agency
3 Entitlement (CUP / site plan) local Local zoning code; Gov. Code 65000 et seq.
4 CEC authorization (SPPE / AFC)
applies onsite generation of 50 MW or more
regulator Pub. Res. Code 25500 et seq.
5 Natural gas service
applies where the facility uses natural gas
utility Serving gas utility tariff
6 Grid interconnection utility Serving utility Rule 21 or CAISO wholesale interconnection
7 Sewer will-serve utility Serving sanitation district or city sewer authority
8 Will-serve letter / water supply assessment utility Water Code 10910 (SB 610); Gov. Code 66473.7 (SB 221) for large projects
9 Building permit local California Building Standards Code (Title 24)
10 Stormwater (construction general permit)
applies where land disturbance is one acre or more
regulator State Water Board Construction General Permit
11 Air district permit (generators) regulator District Authority to Construct and Permit to Operate under Health & Safety Code 42300
12 Public agreements and incentives
applies where negotiated with the host jurisdiction
local Development agreements, Gov. Code 65864 et seq.

Steps are shown in their typical order; steps at the same stage usually run concurrently, and conditional steps apply only where noted. Per-facility status against this path is tracked at ComputeCompute.

California Building Standards Code (Title 24)

The statewide building code local building departments enforce; the building permit for the structure itself issues under the local adoption of Title 24.

Citation
Cal. Health & Safety Code 18901 et seq.; 24 Cal. Code Regs.
Status
In force
Applies to
Both
Source
Cal. Health & Safety Code 18901 et seq.; 24 Cal. Code Regs.

Construction general permit (stormwater)

Construction disturbing one acre or more requires coverage under the statewide construction general permit administered by the State Water Resources Control Board.

Citation
State Water Board Order WQ 2022-0057-DWQ (NPDES No. CAS000002), under Cal. Water Code 13260 et seq.
Status
In force
Applies to
Both
Source
State Water Board Order WQ 2022-0057-DWQ (NPDES No. CAS000002), under Cal. Water Code 13260 et seq.

Warren-Alquist Act (CEC siting; small power plant exemption)

Thermal power plants of 50 MW or more require California Energy Commission certification; backup generation fleets at that scale proceed through the small power plant exemption (SPPE) docket, which produces a CEQA-equivalent record at the Commission.

Citation
Cal. Pub. Res. Code 25500 et seq.
Status
In force
Applies to
Both
Source
Cal. Pub. Res. Code 25500 et seq.

California Environmental Quality Act (CEQA)

Requires environmental review of discretionary approvals. The land-use authority is usually the lead agency for a data-center entitlement; the record produced (exemption, negative declaration, or EIR) is the project's central public document set.

Citation
Cal. Pub. Res. Code 21000 et seq.
Status
In force
Applies to
Both
Source
Cal. Pub. Res. Code 21000 et seq.

Development agreements

Authorizes negotiated agreements between a developer and the host jurisdiction fixing rules and exactions for a project. Where a data center has negotiated fiscal or infrastructure terms, this is the usual vehicle and the agreement is a public record.

Citation
Cal. Gov. Code 65864 et seq.
Status
In force
Applies to
Both
Source
Cal. Gov. Code 65864 et seq.

Planning and Zoning Law

The enabling framework for local general plans, zoning, and discretionary entitlements. A data center's conditional use permit, site plan, or rezoning is issued by the city or county under its zoning code adopted under this law.

Citation
Cal. Gov. Code 65000 et seq.
Status
In force
Applies to
Both
Source
Cal. Gov. Code 65000 et seq.

District air permitting (authority to construct; permit to operate)

Local air districts permit stationary sources. A data center's diesel or gas generator fleet requires a district authority to construct and permit to operate; district registers are a primary public record of fleet size and fuel.

Citation
Cal. Health & Safety Code 42300 et seq.
Status
In force
Applies to
Both
Source
Cal. Health & Safety Code 42300 et seq.

SB 221 written verification of water supply

Requires written verification of sufficient water supply as a condition of approving certain large subdivisions; the companion statute to SB 610 in linking land-use approval to demonstrated supply.

Citation
Cal. Gov. Code 66473.7
Status
In force
Effective date
2002-01-01
Applies to
Both
Source
Cal. Gov. Code 66473.7

SB 610 water supply assessments

Large projects subject to CEQA require a water supply assessment from the public water system that would serve them, documenting whether projected supplies cover the project over 20 years.

Citation
Cal. Water Code 10910 et seq.
Status
In force
Effective date
2002-01-01
Applies to
Both
Source
Cal. Water Code 10910 et seq.

Reviewed 2026-07-24. Confidence: high. Fast-moving area, verify before relying. Not legal advice.